Prioritize process order to sequence first in PPDS optimization run

$
0
0

Hi Guru,

We are running optimization in PPDS in DS board, when we run optimization we have process order

which are in created statues and planned order in firmed statues. We had product priority in Optimization profile.

 

Issue:

When we run the optimization run we see process order were moving out and planned order firmed & planned order

created are coming in front and pushing process order all the way out.

 

Please suggest if there is a way to sequence the process order first and then planned order firmed .

 

Waiting for response

 

Thanks in advance

 

Thanks & Regards,

Rajesh