Dear Expert
We are trying to run rescheduling function for all resources in ZBiomet in background job with /SAPAPO/CDPSB0, and consider order internal relationship in the strategy profile, but this kind of job will be cancelled,
With the following error messages:
Normally, this kind of error message means some of the resources are not included in the rescheduling run, but we have selected all resources in ZBiomet.
If we reschedule all the resources with strategy profile which doesn’t consider the order internal relationship, then this job can be completed without error, but Basically, the order internal relationship should be considered in rescheduling.
Due to this job fails, we can’t give a complete planning result to customer, Would you please further check on it why this job will be cancelled?
BTW, We’ve debugged on the program, found in FM /SAPAPO/OM_ACT_SCHEDULE if the strategy profile consider the order internal relationship, then ET_RC will have data, and then will lead to cancel the job.
any post would be helpful for us.
Thanks
Kevin