Hi Experts,
We have some resources which are missing in APO as they were earlier marked as non-APO relevant in ECC. Now we need to schedule them in APO --so they are being marked as APO relevant in ECC.
I understand that resources need to be CIFed to APO and also PDS need to be integrated again as some of the the resources which were excluded earlier in the PDS --now need to be integrated.
As per my understanding the steps of integration will be --
1. Recreate and reactivate Resource CIF Integration Model.
2. Transfer all PDS again using CURTO_CREATE in ECC.
3. I think there is no need to recreate and reactivate PDS integration model.
Can you please help and verify above points and add if I am missing any point ? Will appreciate some help.
Regards
Learner