Hi Gurus,
We have a scenario where we have finished product is getting packed from vendor to DC plant A .
Where as component is produced in plant B.Please suggest where we can have a BOM for finished product
where the component need to produced in different plant.Please suggest
12345--Finished Product ---> Procured from sub-contracting vendor to plant A as selling is done to customer from plant A
1000001111 Semi-Finished product is produced in Plant B
Please suggest how BOM need to be updated.
Thanks in Advance
Thanks & Regards,