Dear Experts,
I have an issue with the SAP_PP_020 heuristic. The problem is that the LLC is not calculated for the components that are externally procured.
The components are included in a PDS for the FG. They do not have a source of supply (the info record is not CIF-ed at the moment).
The SAP_PP_020 heuristic is returning the following message: "No supply sources were found for the model 000".
My question is: Is it necessary to have a source of supply for the component? What workaround do you propose?
Thank you in advance,
Hrvoje