PPDS Resource Constraint Planning for Multiple Source of supply

$
0
0

Hello,

 

We have a scenario, where we are creating Multiple Production versions which CIF to APO with Multiple PDS. In multiple PV different work centers & different BOM has been assigned… We want to do Capacity planning for all Source of Supply.

 

I see only option is to use SAP_REM heuristic…But we don’t want to use this heuristic, as it is having lots of restriction…

 

I have tried with SAP PP heuristic for creating planned orders, and then doing capacity planning using SAP_DS_02…Enhanced Backward scheduling & SAP_DS_01 Stable Forward Scheduling … But it is still doesn't select the alternative source of supply…

 

Is there any heuristic, or running multiple sequence of heuristic which can plan on multiple PDS for capacity leveling …..

 

 